Multi-Year Infrastructure Modernization (1,200+ Employees)
Case study 02 · IT Project Manager & Infrastructure Lead · Applied Materials · 2023–2026

Context
Overhaul of R&D and production IT infrastructure supporting a facility of 1,200+ employees.
Challenge
High-stakes delivery across R&D, IT, Finance, and external contractors, with strict production schedules and long-lead hardware bottlenecks.
Actions
- Translated R&D technical requirements into bills of materials and procurement schedules.
- Tracked dozens of long-lead items end to end, from vendor sourcing through installation and handover.
- Built one automated SQL and Tableau dashboard per project, giving tens of executives live visibility into milestones, risks, and budget.
- Moved server workloads to a colocation site.
Results
- 30% lower compute cost after moving servers to a colocation site.
- On-time milestones with no downtime to R&D schedules during the upgrade.
- Full executive visibility: Manual status reporting replaced by real-time KPI dashboards.
- Streamlined forecasting: Recurring budget cycles run in step with Finance and Purchasing.
What I’d do differently
I’d assign an owner to every dashboard input on day one. A dashboard is only as reliable as the data feeding it, and keeping inputs current turned out to be its own ongoing effort, not a one-time build.
Artifacts
An illustrative program view reconstructed from the format actually used, not the real dashboard, all on synthetic sample numbers: schedule risk by workstream (Finance, IT, R&D, contractor teams), a multi-workstream timeline, and budget utilization over time. Click a workstream to see its status detail.
Schedule risk by workstream
Click a workstream for its status detail.
Q3 forecast submitted on schedule, no open budget risks.
Network-gear procurement for the new office is running about two weeks behind.
Lab buildout milestones are tracking to plan.
General contractor flagged a schedule slip on the core office buildout.
Multi-workstream timeline
Dashed line marks today; bars are each team's active build phase.
Budget utilization over time
Illustrative reconstruction of the format on synthetic sample numbers, not the real dashboard or real figures.